Correction: Date/Time of Initial Impact: August 6, 2018 0021Z

Update #1:
The issue is resolved as of 0236z and data flow has resumed. The issue was with PDA's ability to inventory GOES-16, GOES-17, SNPP, and JPSS1 data in its database. All data missed during the window is expected to be made up through normal reconciliation processes.

Topic:
GOES-16 and NPP data is delayed to PDA.

Date/Time Issued: August 6, 2018 0350Z

Product(s) or Data Impacted: GOES-16 and NPP data to PDA.

Date/Time of Initial Impact: August 6, 2018 0021Z

Date/Time of Expected End: August 6, 2018 0236Z

Length of Event: 2 hours 15 minutes

Details/Specifics of Change: Technicians are working on issue.

Contact Information for Further Information: ESPC.Notification@noaa.gov

This message was sent by ESPC.Notification@noaa.gov You have been sent this and other notifications because you have opted in to receive it. If for any reason, you wish to unsubscribe, please contact ESPC Help Desk at ESPCOperations@noaa.gov or 301-817-3880. Please note: it may take up to two business days to process your unsubscribe request.