Topic: NOAA-20 Risk Mitigation Maneuver (RMM)
scheduled for June 19, 2019
Date/Time Issued: June 18, 2019 2317Z
Product(s) or Data Impacted: All NOAA-20 Sensor Data
Date/Time of Initial Impact: Primary, June 19, 2019 19:05z
/ Secondary, June 20, 2019 01:44z
Date/Time of Expected End: Primary, June 19, 2019
21:12z / Secondary, June 20, 2019 03:51z
Length of Outage: See Details.
Details/Specifics of Change: On June 19, 2019 at 19:31Z,
NOAA-20 (JPSS-1) will perform a propulsive collision Risk
Mitigation Maneuver
(RMM)to mitigate a close approach with orbital debris. If the
maneuver can not be executed during the primary opportunity, a
contingency maneuver opportunity is planned for June 20, 2019 at
02:10z. Only one maneuver will be executed. This activity is
subject to change based on changes to the close approach risk.
The following observatory systems will be affected on June 19/20,
2019. The times below are as planned, but actual on-orbit
execution times may be offset by a few seconds.
Primary Burn Times, June 19 2019:
19:05:00Z M-bM-^@M-^S 21:12:02Z M-B CERES in Contam-Safe mode, science data
will not be available
19:15:00Z M-bM-^@M-^S 19:41:02Z M-B M-BOMPS in Decon mode, Science data will not
be available
19:20:02Z M-bM-^@M-^S 19:43:02Z M-BHRD will be off, data for direct broadcast
users will be unavailable
19:31:00z Thruster firing, NOAA-20 will remain
in Mission Point, however, there may be thruster firing
induced attitude errors for a few minutes after thruster
firing. Any collected data during that time period may be
impacted and not disseminated.
Secondary Burn Times, June 20 2019:
01:44:00Z M-bM-^@M-^S 03:51:02Z M-B CERES in Contam-Safe mode, science data
will not be available
01:55:00Z M-bM-^@M-^S 02:20:02Z M-B M-BOMPS in Decon mode, Science data will not
be available
01:59:02Z M-bM-^@M-^S 02:22:02Z M-BHRD will be off, data for direct broadcast
users will be unavailable
02:10:00z Thruster firing, NOAA-20 will remain
in Mission Point, however, there may be thruster firing
induced attitude errors for a few minutes after thruster
firing. Any collected data during that time period may be
impacted and not disseminated.
Contact Information for
Further Information: ESPC Operations at ESPCOperations@noaa.gov
at 301-817-3880
Web
Site(s) for applicable information: N/A
This
message was sent byESPC.Notification@noaa.gov.
You have been sent this and other notifications because
you have opted in to receive it. If for any reason, you
wish to unsubscribe, please contact
ESPC Help Desk atESPCOperations@noaa.gov or(301) 817-3880. Please
note: it may take up to two business days to process your
unsubscribe request.