Topic: GOES-17 (GOES-West) ABI Cooling Timeline Test scheduled for October 15, 2019, Issued: October 15, 2019 1530Z
Date/Time Issued: Oct 15, 2019 1433Z
Product or Data Impacted: GOES-17 ABI L1b Band 02 and derived products All Scenes delivered to AWIPS, GRB, PDA.
Date/Time of Initial Impact: Oct 15, 2019 1100Z
Date/Time of Expected End: Oct 15, 2019 1200Z
Length of the Outage/Event: 1 hour
Details/Specifics of Change: GOES-17 ABI L1b Band 02 and
derived products All Scenes delivered to AWIPS, GRB, PDA. The Data
Impacts of the test were as expected/described with the
expectation of missing Band 02 imagery at 1130Z. Post test there
were 1 FD, 2 CONUS, 10 MESO1 and 10 MESO2 images missing as well.
Root cause of these Band 02 impacts are under investigation.
Contact information for further information: ross.cox@noaa.gov
Web Site(s) for applicable information:
See https://www.ospo.noaa.gov/Operations/messages.html for this and other satellite related messages.
This message was sent to ESPC.Notification@noaa.gov. You have been sent this and other notifications because you have opted in to receive it. If for any reason, you wish to unsubscribe, please contact ESPC Help Desk at ESPCOperations@noaa.gov or (301) 817-3880. Please note: it may take up to two business days to process your unsubscribe request.