Topic: Planned Maintenance Impacting ESPC
Legacy Production Systems
Date/Time Issued: July 21, 2021 1800Z
Product(s) or Data Impacted: A wide range of products
will be impacted. Please see the list in the details section below.
Date/Time of Initial Impact: July 21, 2021
1700Z
Date/Time of Expected End:
July 21, 2021 2030Z
Length of Outage: 180 minutes. No data will be lost, just
delayed.
Details/Specifics of Change: ESPC Legacy
production systems will be rebooted as part of
routine system maintenance. The outage should not result in any
products being incomplete or lost, but data delivery will be
delayed. Shown below is a detailed listing of impacts to products.
PRODUCTS UNAVAILABLE DURING MAINTENANCE
- SSMI / SSMIS TDRs, SDRs, RDRs
- GOES
-- POES / MetOp Level 1B, 1B*, Granules:
-- AMSU-A
-- AVHRR FRAC / GAC
-- DCS
-- GOME
-- HIRS
-- HRPT
-- MHS
-- SBUV
-- SEM
PRODUCTS DEGRADED or UNAVAILABLE DURING MAINTENANCE:
These are POES / MetOp derived products that use 1Bs, 1B*s,
Granules:
- ACSPO
- ATOVS
- bRR
- BTPW
- CLAVR-X
- Coastwatch AVHRR
- GOME
- GVI (short Polarprod outage will have minimal impact to this
daily product)
- GVPS (short Polarprod outage will have minimal impact to this
daily product)
- HMS (short Polarprod outage will cause only short delay to
polarimagery)
- IASI
- IMS-24 (short Polarprod outage will cause only short delay to
polarimagery)
- IMS-4 (short Polarprod outage will cause only short delay to
polarimagery)
- MGVI
- MIRS
- MSPPS
- MSPPS-AOI
- POES-SST/Aerosol
- PolarMapping
- RadBud
- SBUV V8
- SMOPS
- SST & Aerosols
- TOAST (short Polarprod outage will have minimal impact to
this daily product)
Web Site(s) for applicable information:
This message was sent by
ESPC.Notification@noaa.gov. You have been sent this and other notifications because you have opted in to receive
it. If for any reason, you wish to unsubscribe, please contact ESPC Help Desk at
ESPCOperations@noaa.gov or (301) 817-3880. Please note: