Update #1: This is a reminder that the GOES-17 ABI FPM Setpoint Changes start tomorrow, April 8, 2022 at 1500 UTC.


Topic: GOES-17 ABI FPM Setpoint Changes April 8-29, 2022

 

Date/Time Issued: April 7, 2022 1300 UTC

 

Product(s) or Data Impacted: GOES-17 (GOES-West) ABI bands 

 

Date/Time of Initial Impact: April 8, 2022 1500 UTC  

 

Date/Time of Expected End: April 29, 2022 1500 UTC 

 

Length of Outage:  21 days

 

Details/Specifics of Change:

 

From April 8, 2022 through April 29, 2022, the operational setpoint of  GOES-17 ABI will be adjusted to mitigate the impacts of the elevated focal plane module (FPM) temperatures on imagery and maintain the maximum nominal hours of water vapor imagery.  See GOES-17 ABI Saturation Prediction Reference Tools for more background information.  


The following table summarizes the adjustments to setpoint throughout the April warm period (changes to setpoint are performed at 1500 UTC):


Dates

Setpoint

April 8-10

90 K

April 11-18

92.8 K

April 19-20

90 K

April 21-29

87 K


These setpoint changes are independent of the GOES-15 supplemental operations plan scheduled for April 12-18, 2022. These changes are not subject to critical weather day.


Contact Information for Further Information: Joseph.Fiore@noaa.gov, or SPSD User Services at SPSD.UserServices.noaa.gov  SPSD.UserServices.noaa.gov

 

This message was sent to ESPC.Notification@noaa.gov. You have been sent this and other notifications because you have opted in to receive it. If for any reason, you wish to unsubscribe, please contact ESPC Help Desk at ESPCOperations@noaa.gov or (301) 817-3880. Please note: it may take up to two business days to process your unsubscribe request.