Update #1:All products and derived products delivered to PDA, GRB and AWIPS are nominal.

Topic: GOES-16 All Products and derived products delivered to PDA, GRB and AWIPS
 
Date/Time Issued:  January  26, 2024 2131Z
 
Product or Data Impacted: GOES-16 Products and derived products All Scenes delivered to PDA, GRB and AWIPS. ABI L1B bands 4 and 14.
 
Date/Time of Initial Impact:  January   26, 2024 1856Z
 
Date/Time of Expected End: January 26, 2023 2030Z
 
Length of the Outage/Event: 94 minutes

 
Details/Specifics of Change: GOES-16 All Products and derived products All Scenes delivered to PDA, GRB and AWIPS.
ABI KPP's bands 4 and 14 impacted.
 
Contact information for further information: ESPC Operations at ESPCOperations@noaa.gov or 301-817-3880 24x7 or goes-r.product.engineering.group@noaa.gov during normal business hours

Web Site(s) for applicable information: N/A


This message was sent by ESPC.Notification@noaa.gov. You have been sent this and other notifications because you have opted in to receive it. If for any reason, you wish to unsubscribe, please contact ESPC Help Desk at ESPCOperations@noaa.gov or (301) 817-3880. Please note: it may take up to two business days to process your unsubscribe request.