Update #4: Cal/Val teams have cleared NOAA-21 CrIS products for operational use. PDA OPS requests for all NOAA-21 CrIS science products will be enabled at 22:00 UTC on June 22, 2024. Direct Broadcast (DB) users can use the equivalent NOAA-21 CrIS science Community Satellite Processing Package (CSPP) LEO products for operations.


Update #3:  ATMS was placed in operational state on Jun 22, 2024 09:28:38 UTC. OMPS was placed in operational state on Jun 22, 2024 11:11:15 UTC.  VIIRS was placed in operational state on Jun 22, 2024 09:33:57 UTC. CrIS was placed in operational state on Jun 22, 2024 12:53:30 UTC. X-Band High Rate Date (HRD) was enabled on Jun 22, 2024 16:15:33 UTC Svalbard pass 8376. 

Cal/Val teams have conducted an assessment of NOAA-21 products and have cleared ATMS and VIIRS products for operational use. PDA OPS for all NOAA-21 ATMS and VIIRS science products will be enabled at 16:45 UTC on June 22, 2024. Direct Broadcast (DB) users can use the equivalent NOAA-21 science Community Satellite Processing Package (CSPP) LEO products for operations.

CrIS products are still recovering and are expected to be released Sunday, June 23, 2024. 

OMPS products are still recovering and are expected to be released on Thursday, June 27, 2024. 

While CrIS and OMPS data are available for Direct Broadcast (DB) users, they have not yet been cleared for operational use.


Update #2 : Spacecraft returned to Mission Pointing mode on June 22, 2024 07:49:52 UTC on
Rev 8371. Instruments will be returned to operations over the next several passes.
All science data from all instruments on NOAA-21 is offline until instrument recovery and cal/val checkout is complete.


Update #1: N21 is in earthpoint and all instruments are in safe mode. Engineering is continuing to investigate.

Topic: JPSS N21 SMD Data Delay
Date/Time Issued: June 22, 2024 2205Z  
 
Product(s) or Data Impacted: JPSS N21 Data Products
 
Date/Time of Initial Impact: June 22, 2024 0424Z       
  
Date/Time of expected end Time: TBD

Length of Outage: TBD
 
Details/Specifics of Change: IDPS is not receiving N21 SMD data until further notice. Engineering is investigating.


Contact Information for Further Information: ESPC Operations at ESPCOperations@noaa.gov at 301-817-3880
 
Web Site(s) for Applicable Information: N/A
 
This message was sent by ESPC.Notification@noaa.gov. You have been sent this and other notifications because you have opted in to receive it. If for any reason, you wish to unsubscribe, please contact ESPC Help Desk at ESPCOperations@noaa.gov or (301) 817-3880. Please note: it may take up to two business days to process your unsubscribe requ