Fwd: requested N15 avhrr ops plans for September

All,
The following information is being forwarded to you to keep you abreast of
plans to enable further analysis of the AVHRR problem on the NOAA-15
spacecraft. Please review it and send any comments or concerns to me as
soon as possible.
Thank you
Emily

>> After a well attended meeting on Monday, August 21st by representatives
>> of OSD, SAO, IPD, and OSO, the following operating conditons for
>> NOAA-15 were requested for scheduling of tests to begin on September
>> 5th and continue for 2 weeks, through September 18th. This test period
>> is limited to 2 weeks based on: 1) the scheduling software (SOMS) -
>> current software has not been used operationally during a launch and
>> NOAA-L is scheduled to be launched September 20th; also 2) Two passes
>> per day for two weeks (28 passes) will give the equivalent of 2 full
>> days worth of data to analyze.
>

>> With this reasoning the following actions are requested of the listed
>> groups.
>>
>> Scheduling (SOCC)
>> 1) Select the passes preceding 2 high elevation (>35 degrees) downlink
>> passes each day (preferably day staff passes) and begin a stored-AIP
>> (SAIP) record then command the MIRP into AVHRR sync mode. The normal
>> GAC recording should continue to be routinely scheduled, i.e., the SAIP
>> will "shadow" the GAC record. At the end of each SAIP "shadow" pass,
>> the MIRP should be commanded back to internal sync (current operating
>> mode).
>>
>> 2) On the high elevation pass after the "shadow" SAIP recording, the
>> SAIP and GAC will be "played down" from the spacecraft , and transferred
>> post-pass with the SAIP transferred to IPD first (at their request) for
>> level 1B processing.
>>
>> SOCC engineering
>> 3) For internal analysis, using the new PIDES, produce soft and hard
>> copies of the HRPT and GAC data from the two passes where the MIRP is
>> switched to AVHRR sync. This should include the real-time dataset
>> showing the switch from internal to external sync and the return to
>> internal sync.
>>
>> The objective of this test is to determine what effects the AVHRR
>> re-syncing has on the MIRP dataset production. Currently, whenever the
>> AVHRR re-syncs, it perturbs the MIRP sampling process, and therefore,
>> the GAC dataset production (effecting all AIP data). With the SAIP
>> "shadow" recording, an AVHRR event will NOT effect the SAIP dataset
>> (different processor), therefore, the current anomaly investigation team
>> will have information to use in investigating the cause and effects of
>> the problem and the other operational instrument datasets will not be
>> compromised.
>>
>> From an operations standpoint, both CDAs have been functionally tested
>> for receiving and transferring SAIP to IPD and the 13m and IMUX
>> recorders have been "set-up".
>>
>> Should any deviation of the test plan outlined above be required,
>> notification and approval of all members of the investigation team will
>> be required.
>

Emily D. Harrod
NOAA/NESDIS/OSDPD/IPD
E/SP13 Room 0308 FB#4
5200 Auth Road
Suitland, Md. 20746-4304
(301)-457-5247 phone


ppp@nesdis.noaa.gov